Controversial tender haunts Kerawalapitiya power plant

The awarding of the 300 MW (LNG) Combined Cycle Kerawalapitiya power plant tender is set to drag on further owing to certain disagreements in opening the financial bid of Samsung JV Korea Group without considering bids of seven other firms.

This decision was taken by the Standard Cabinet Appointed Procurement Committee (SCAPC) amidst disagreement of the Technical Evaluation Committee (TEC), a senior official of the Power and Renewable Energy Ministry said. Plans to build the power plant were suspended after detecting certain irregularities in the tender procedure to select the company to construct the plant. The LNG power project has been in the planning stage for the last 10 years. The disqualified bidders’ can make their submissions to the Appeal Board against the SCAPC decision, Secretary to the Ministry Dr. Suren Batagoda told the Business Times.

The current controversial tender under criticism of CEB engineers and energy experts is likely to be referred to the Procurement Appeal process, he opined. He disclosed that he has already submitted his observations to the cabinet stating that all eight bids which passed in commercial evaluation should be re-considered in awarding this tender.

The bidding process consisted of three stages; commercial evaluation, technical evaluation and the financial evaluation. Out of eight bidders, seven bidders had been disqualified at the technical evaluation stage as they have failed to fulfill minimum functional specifications. Under this set up only Samsung Korea has qualified to be evaluated for the financial evaluation, he added. However he noted that he has made a recommendation to allow the seven disqualified firms to rectify their technical shortcomings and open all of their financial biddings. While rejecting two bids, TEC has recommended to SCAPC to open the financial bids of all six bidders who have passed the technical evaluation. But SCAPC has selected only Samsung JV of Korea and disqualified five bidders disregarding the TEC recommendations, CEB engineers union alleged.

Lankanewspapers

Recent Posts

LNP – New vehicle shipment to touch down today

As the first shipment of vehicles is expected to arrive in Sri Lanka today since…

14 hours ago

LNP – Cabinet approves E-8 visa jobs for Sri Lankans, exclusively through SLBFE

The Cabinet approved employment opportunities under South Korea’s E-8 visa category, with recruitment exclusively handled…

14 hours ago

LNP – Woman arrested at BIA with 1.2 kgs of kush

A 38-year-old woman was arrested at the Bandaranaike International Airport (BIA) while attempting to smuggle…

14 hours ago

LNP – Namal Rajapaksa arrives at CID to record statement over Airbus deal

Sri Lanka Podujana Peramina (SLPP) Parliamentarian Namal Rajapaksa has arrived at the Criminal Investigation Department…

14 hours ago

LNP – Showers above 75mm expected in parts of the island

The Department of Meteorology says that showers or thundershowers will occur at times in Northern,…

14 hours ago

LNP – First batch of imported personal vehicles arrives at Colombo Port after 5-year hiatus

The first batch of vehicles imported for private use arrived at the Colombo Port on…

14 hours ago